The Data Center Debate

By state

Data centers in Florida

13 data centers and projects on our map in Florida, including 3 projects we track in detail. Each one links to its source. Below: where they are by county, the projects in the news, and the latest reporting from both sides.

See Florida on the map. Existing facilities come from OpenStreetMap, a community-maintained public map that is incomplete; proposed, under construction and blocked projects are tracked one by one from news, filings and official records.

Projects in the news

Blocked, paused or withdrawn 12 month moratorium in effect from 2026-09-22

Manatee County Data Center Moratorium

Bradenton, Manatee County

announced 2026-09-22

Manatee County's one year moratorium took effect September 22 and blocks large load customers or facilities with substantial utility demands from applying for building permits, site plans, rezones or comprehensive plan amendments. The county cites Florida Senate Bill 484 as authority.

Issues raised: power, water, zoning, opposition

Source: Your Observer, 2026-09-22 · On the map

Blocked, paused or withdrawn 18 month moratorium approved September 22, 2026

North Port Data Center Moratorium

North Port, Sarasota

announced 2026-09-22

The North Port City Commission gave final approval to an 18 month moratorium on new data center applications after a hearing that drew hundreds of residents citing water, noise, air quality and jobs concerns. One pending application for a 900,000 square foot project is exempted.

Issues raised: water, noise, opposition, zoning

Source: Sun Newspapers, 2026-09-22 · On the map

Blocked, paused or withdrawn Ordinance prohibiting data centers adopted unanimously on 2026-09-22

Wakulla County Data Center Ban

Crawfordville, Wakulla County

announced 2026-09-22

Wakulla County commissioners unanimously approved an ordinance amending the Land Development Code to prohibit data centers in unincorporated areas of the county. Public comment focused on water concerns tied to Wakulla Springs and the surrounding cave system.

Issues raised: water, opposition, zoning

Source: WCTV, 2026-09-22 · On the map

By county

  • Manatee County 1 on the map
    Manatee County Data Center Moratorium
  • Sarasota 1 on the map
    North Port Data Center Moratorium
  • Wakulla County 1 on the map
    Wakulla County Data Center Ban

Latest news from Florida

Supports the case against local September 22, 2026

North Port Florida approves 18 month data center moratorium

The North Port City Commission gave final approval to an 18 month moratorium on new data center applications after a packed public hearing that ran nearly seven hours. Residents cited concerns about water supply, noise, air pollution and job claims; one pending application from a 900,000 square foot project is unaffected. The commission said the pause allows time to write local rules.

Sun Newspapers Water use Local opposition and consent Noise, appearance and rural character

Check it: Whether the exempted 900,000 square foot project proceeds and whether the city develops permanent standards during the 18 months.

Supports the case against local September 22, 2026

Wakulla County commissioners adopt permanent data center ban

Wakulla County commissioners voted unanimously to adopt an ordinance prohibiting data centers in the county's unincorporated areas, formalizing a ban that county staff said had been in effect in practice. Speakers at the public hearing raised concerns about impacts on Wakulla Springs and the groundwater system.

WCTV Local opposition and consent Water use Siting, zoning and standards

Check it: The ordinance applies only to unincorporated Wakulla County and can be amended by future commissions.

Supports the case against local September 22, 2026

Manatee County one year data center moratorium takes effect

Manatee County's 12 month moratorium began September 22, preventing large load customers or facilities with substantial electric, water, wastewater or other utility demands from submitting building permits, site plans, rezones or comprehensive plan amendments. The county cited Senate Bill 484 as authority for the pause.

Your Observer Laws, bills and regulation Siting, zoning and standards Water use

Check it: The moratorium covers all large load facilities, not only data centers, and its enforcement depends on how the county interprets substantial utility demands.

Weighing it up

For the arguments behind these fights, see the case for data centers, the case against, and the questions people ask, each answered from both sides.