The Data Center Debate

By state

Data centers in Louisiana

2 data centers and projects on our map in Louisiana, including 2 projects we track in detail. Each one links to its source. Below: where they are by county, the projects in the news, and the latest reporting from both sides.

See Louisiana on the map. Existing facilities come from OpenStreetMap, a community-maintained public map that is incomplete; proposed, under construction and blocked projects are tracked one by one from news, filings and official records.

Projects in the news

Proposed Announced August 2026, third campus in the Caddo Bossier area

AWS Shreveport Third Data Center Campus

Shreveport, Caddo Parish · Operator: Amazon Web Services

$6 billion · announced 2026-08-18

Amazon Web Services announced a third campus in the Shreveport area, reported at about 6 billion dollars and bringing its stated Caddo Bossier total to roughly 18 billion dollars. Louisiana has offered substantial incentives to attract data centers.

Issues raised: power, water, tax-incentives, jobs

Source: KSLA, 2026-08-18 · On the map

Under construction Building since late 2024, expanded to 5 gigawatts in 2026, phased through 2032

Hyperion

Delhi, Richland Parish · Operator: Meta

5000 MW · $50 billion · announced 2024-12

Meta's largest AI campus, roughly four million square feet on about 2,250 acres in rural northeast Louisiana, supported by new gas fired generation built by Entergy. It is a leading example in arguments about who pays for the power plants and transmission that serve a single customer.

Issues raised: power, air-pollution, water, tax-incentives, transmission, jobs

Source: Data Center Frontier · On the map

By county

  • Caddo Parish 1 on the map
    AWS Shreveport Third Data Center Campus
  • Richland Parish 1 on the map
    Hyperion

Latest news from Louisiana

Cited by both sides policy October 7, 2026

Louisiana PSC opens three day hearing on Entergy's $12.9 billion power plan for Meta Hyperion

The Louisiana Public Service Commission opened an October 7 to 9 evidentiary hearing on Entergy Louisiana's request to spend about $12.9 billion on seven gas plants, a 500 kV transmission line, solar and batteries to serve Meta's Hyperion data center in Richland Parish. Entergy and PSC staff have a settlement in hand. Opponents argue the risk to other ratepayers is too high if Meta's load does not materialize. A commission decision is scheduled for December 16.

The Advocate Who pays for the grid buildout Who holds the risk How much electricity data centers use Air quality and on-site power

Check it: Look at who holds the stranded cost risk in the settlement if Meta's expansion scales back. A ratepayer protection clause only matters if it is enforceable.

Cited by both sides policy October 2, 2026

Louisiana PSC to hold three day evidentiary hearing on Entergy's Meta data center buildout

The Louisiana Public Service Commission is scheduled to begin an evidentiary hearing on October 7 on whether Entergy Louisiana can build seven generators totaling 5,278 MW along with batteries and transmission to serve Meta's $50 billion Richland Parish campus, and on how cost and stranded investment risk should be allocated. The Alliance for Affordable Energy, Union of Concerned Scientists and Sierra Club are listed as participants, with a commission decision targeted for December 16.

10/12 Industry Report Who pays for the grid buildout Who holds the risk How much electricity data centers use

Check it: The hearing is before an administrative law judge; the commission vote in December is what sets who pays.

Supports the case for policy September 29, 2026

Louisiana Gov. Landry defends data center buildout, compares water use to golf courses

At a State of the State luncheon in Monroe, Gov. Jeff Landry said data center companies have pledged not to raise residential electricity rates and dismissed water concerns by saying U.S. golf courses use about 500 billion gallons a year versus roughly 18 billion for data centers. Several Louisiana data centers are under construction, including Meta's Hyperion campus in Richland Parish.

Louisiana Radio Network Water use Who pays for the grid buildout How much electricity data centers use

Check it: Landry's water and rate claims are political statements; the pledges have not been reduced to enforceable tariffs, and data center water use projections vary widely by cooling design.

Weighing it up

For the arguments behind these fights, see the case for data centers, the case against, and the questions people ask, each answered from both sides.