Blocked, paused or withdrawn City council voted 7 to 1 in May 2026 to make its data center ban permanent
City of St. Charles Data Center Ban
St. Charles, St. Charles County
St. Charles made permanent a one year moratorium adopted after widespread opposition to a proposed data center of about 1 billion dollars off Highway 370. St. Charles County separately approved a six month countywide pause in July 2026.
Issues raised: zoning, water, power, opposition
Source: St. Louis Public Radio, 2026-05-20 · On the map
Blocked, paused or withdrawn Board of Aldermen removed data centers from the zoning ordinance, blocking the project
Project Harper
Peculiar, Cass County · Operator: Diode Ventures
$1.5 billion · announced 2024-01
A proposed 504 acre data storage and technology park south of Kansas City. After hundreds of residents from Peculiar and Raymore objected, the Board of Aldermen reversed course and stripped the data center definition from the light industrial zoning code.
Issues raised: zoning, opposition, power, water
Source: Data Center Dynamics, 2024-10 · On the map
Proposed developer sued city September 17 over renewables and community benefits conditions
Armory Data Center (former Famous-Barr warehouse)
St. Louis, St. Louis City · Operator: TerraWatt
120 MW · $3.1 billion
TerraWatt is planning a $3.1 billion, 120 megawatt data center on 11 acres in Midtown St. Louis. The developer sued the city on September 17 over a use permit requirement to install 2.4 megawatts of on-site renewables and to secure Board of Aldermen approval of a community benefits agreement.
Issues raised: opposition, power, zoning, air-pollution
Source: STLPR, 2026-09-17 · On the map
Proposed Announced May 2026, described as one of the largest tech investments in state history
Google Montgomery County Campus
Montgomery City, Montgomery County · Operator: Google
$15 billion · announced 2026-05
Google announced a data center campus in rural Montgomery County, Missouri, reported at about 15 billion dollars. Debate centers on electricity demand, water use and the size of state and local incentives.
Issues raised: power, water, tax-incentives, jobs
Source: Oklahoma Energy Today, 2026-05 · On the map
Under construction First building complete, further buildings still being built
Meta Kansas City Data Center
Kansas City, Clay County · Operator: Meta
$1 billion · announced 2022-03
A Meta campus in the Northland section of Kansas City where the first building opened in 2025 and additional buildings remain under construction. The project preceded a 2026 city zoning change that made new data centers harder to approve.
Issues raised: zoning, power, water, jobs, tax-incentives
Source: FOX4 Kansas City · On the map