Blocked, paused or withdrawn Metro Council passed a permit moratorium through December 1, 2026 and banned data centers larger than 500,000 square feet, July 2026
Nashville Data Center Moratorium and Size Cap
Nashville, Davidson County
Nashville adopted its first data center regulations along with a temporary pause on new permits in Davidson County. The votes followed weeks of public pressure, including opposition to a proposed facility next to the Nashville Zoo.
Issues raised: zoning, power, water, noise, opposition
Source: Nashville Banner, 2026-07-21 · On the map
Proposed Final vote postponed to 2026-10-20 after a 7 to 5 delay vote
Memphis Data Center Moratorium
Memphis, Shelby
announced 2026-10-07
Memphis's council voted 7 to 5 to delay its third reading of a 12 month data center moratorium to October 20, 2026, after a meeting that broke down into shouting, protest and a fistfight. The ordinance would pause approvals while the city studies health, power and water impacts; xAI's Colossus facilities drove the opposition.
Issues raised: power, water, air-pollution, noise, opposition
Source: WSMV, 2026-10-07 · On the map
Proposed First reading passed 5-4-4 on October 12, 2026, further readings required
Shelby County Data Center Moratorium
Memphis, Shelby
announced 2026-10-12
Shelby County commissioners passed the first reading of a proposed 12-month pause on data center development in unincorporated parts of the county. The measure sits alongside a separate Memphis city moratorium that returns for its third reading on October 20.
Issues raised: power, water, noise, opposition, zoning
Source: Action News 5, 2026-10-13 · On the map
Under construction First GPU hall running while build out continues
Colossus 2
Memphis, Shelby County · Operator: xAI
announced 2025-02
xAI's second Memphis area supercomputer campus, with an associated turbine fleet across the Tennessee and Mississippi line supplying power. The NAACP and the Southern Environmental Law Center sued over gas turbines operated without federal air permits near homes and a school.
Issues raised: air-pollution, power, water, opposition, noise
Source: Southern Environmental Law Center · On the map
Operating Operating with active air permit litigation
xAI Colossus
Memphis, Shelby County · Operator: xAI
xAI built its Colossus supercomputer in a former factory in south Memphis starting in 2024 and powered it in part with on site methane gas turbines. The NAACP and the Southern Environmental Law Center sued in 2026, alleging the site ran more turbines than its permit allowed and exposed nearby majority Black neighborhoods to additional smog forming and hazardous air pollution.
Issues raised: air-pollution, power, water, opposition, jobs
Source: CNBC, 2026-04-14 · On the map