Blocked, paused or withdrawn Council voted unanimously in August 2026 to begin a 90 day moratorium taking effect February 2027
Fort Worth Data Center Moratorium
Fort Worth, Tarrant County
Fort Worth City Council started the process for a 90 day pause on data center rezoning and permit decisions while staff study noise, water supply and land use compatibility. The zoning commission had rejected an earlier draft ordinance, and residents organized against projects proposed in south Fort Worth.
Issues raised: noise, water, power, zoning, opposition
Source: Fort Worth Report, 2026-08-12 · On the map
Blocked, paused or withdrawn Council voted 4 to 3 on June 16, 2026 to make data centers ineligible in every zoning district
San Marcos Citywide Data Center Prohibition
San Marcos, Hays County
San Marcos became the first Texas city to prohibit data centers citywide, writing them out of its development code after rejecting a rezoning bid earlier in 2026. Council members cited water and energy demands on the local community, and Hays County separately paused data center approvals.
Issues raised: water, power, zoning, opposition
Source: The Texas Tribune, 2026-06-30 · On the map
Proposed Clean air permit granted February 2026, early phases only, first gigawatt targeted for late 2026
Project Matador, HyperGrid Campus
Amarillo, Potter County · Operator: Fermi America
11000 MW · announced 2025-06-26
A proposed 5,800 acre campus on Texas Tech University System land that would pair up to 11 gigawatts of on site nuclear, gas, solar and wind generation with about 18 million square feet of data centers. It would be the largest combined energy and computing complex announced in the United States, and construction paused in early 2026 while the company waited on its state air permit.
Issues raised: power, water, jobs, transmission, air-pollution
Source: KFDA NewsChannel 10, 2026-02-25 · On the map
Proposed Announced July 2026, construction expected to begin late 2026
Childress AI Data Center Campus
Childress, Childress County · Operator: Crusoe and Lancium
1000 MW · announced 2026-07-15
A grid connected AI data center campus of about 270 acres in the Texas Panhandle, with Lancium developing the site energy infrastructure. Backers cite construction jobs and long term tax base in a small rural county.
Issues raised: power, jobs, transmission
Source: Crusoe, 2026-07-15 · On the map
Proposed confirmed by county judge October 9 2026; construction targeted for 2027
Desert Haven Data Center Campus
Sierra Blanca, Hudspeth · Operator: Kaufman and Company
350 MW · $15 billion · announced 2026-10-09
A Kaufman and Company led partnership, including ServerDomes Global, has told Hudspeth County it plans a 24,000 acre campus near Desert Haven with on site electricity generation and 350 megawatts of load. The developer said water will be drawn only once at startup and that no tax abatement is being requested.
Issues raised: power, water, jobs, zoning
Source: KVIA ABC-7 El Paso, 2026-10-09 · On the map
Proposed City commission voted Sept 2, 2026 to draft a 90-day moratorium ordinance on data center rezoning and permits.
Brownsville Data Center Moratorium
Brownsville, Cameron
announced 2026-09-02
Brownsville commissioners directed staff to draft a temporary 90-day pause on new rezoning and permit applications for high-intensity data processing facilities. The move follows Governor Abbott's statewide audit of pending data center grid requests.
Issues raised: zoning, power, opposition
Source: MyRGV, 2026-09-02 · On the map
Proposed Announced 2026, construction not started
CyrusOne Medina County Campus
Hondo, Medina County · Operator: CyrusOne
$500 million · announced 2026-08
A proposed CyrusOne data center campus west of San Antonio reported at about 500 million dollars. Medina County sits over the Edwards Aquifer recharge zone, which has made water the leading local concern for new data center projects in the region.
Issues raised: water, power, zoning, jobs
Source: Data Center Knowledge, 2026-08 · On the map
Proposed Four building campus disclosed in 2026, construction not started
Project Eagle
Wharton, Wharton County · Operator: Amazon Web Services
announced 2026-08
Amazon disclosed plans for a four building data center campus in Wharton County, southwest of Houston. It is one of several new Texas campuses announced in 2026, and local questions center on ERCOT grid capacity and groundwater.
Issues raised: power, water, transmission, jobs
Source: Data Center Knowledge, 2026-08 · On the map
Proposed state filings submitted October 2, 2026; Kent County commissioners tabled tax reinvestment zone vote
Project Hyper, Jayton Campus
Jayton, Kent · Operator: Crusoe
$4.8 billion · announced 2026-10-02
Crusoe filed notices with the Texas Department of Licensing and Regulation on October 2 for two 759,260 square foot buildings in Jayton, Kent County, listed as spur sites of Project Hyper and tied to a combined investment of $4.8 billion. The filings say construction will start in January 2027 and the buildings will use closed-loop cooling.
Issues raised: power, water, zoning, transmission
Source: Data Center Dynamics, 2026-10-02 · On the map
Proposed Annexation agreement approved 5 to 0 on 2026-10-09
Taylor Technology Campus
Taylor, Williamson · Operator: Big Watt Digital and PowerHouse Data Centers
announced 2026-10-09
A 664 acre data center and on site power plant proposed outside Taylor, Texas, previously known as Project Mustang. Taylor approved annexation and a city regulatory agreement with the developers, with about $28.2 million in community investments.
Issues raised: power, water, air-pollution, noise, zoning, jobs
Source: KUT, 2026-10-09 · On the map
Under construction Broke ground 2026, first building due late 2026
Vantage Frontier Campus
Albany, Shackelford County · Operator: Vantage Data Centers for OpenAI and Oracle
1400 MW · announced 2025-09
A 1,200 acre Stargate campus planned for 10 single story data centers totaling about 1.4 gigawatts northeast of Abilene. Supporters point to more than 5,000 construction and operations jobs, while critics focus on the power draw in a rural county.
Issues raised: power, jobs, transmission, water
Source: Data Center Dynamics · On the map
Under construction Under construction with operations expected 2028
Meta El Paso Campus
El Paso, El Paso County · Operator: Meta with BlackRock
1000 MW · $14 billion · announced 2025-10
A one gigawatt Meta campus in the Chihuahuan Desert financed through a venture with BlackRock, with more than 2,000 workers on site and a filing to add twelve more buildings. Water supply in an arid border city and the size of the local incentive package are the main points of contention.
Issues raised: water, power, tax-incentives, jobs
Source: CNBC, 2026-07-28 · On the map
Under construction Construction plans filed; targeted start late November 2026
Project Longhorn
Cedar Creek, Bastrop · Operator: Pacifico Energy and BlackChamber Group
$366 million · announced 2026-10-06
A $366 million, 498,165 square foot data center campus in Cedar Creek, Texas, reportedly in talks to be leased by Anthropic. The project cleared the statewide pause on environmental permit approvals ordered by Governor Abbott.
Issues raised: power, water, zoning
Source: Community Impact, 2026-10-06 · On the map
Under construction Construction under way on a former industrial site
Stargate Milam County
Rockdale, Milam County · Operator: OpenAI with SB Energy
$3 billion · announced 2025-09
One of five Stargate sites announced in September 2025, located on a former aluminum smelter and crypto mining site in central Texas. Local debate centers on the tax abatement package and on how much new generation the campus will require.
Issues raised: power, tax-incentives, jobs
Source: Austin American-Statesman · On the map
Operating First buildings energized September 2025, remaining buildings still in construction
Stargate Abilene, Lancium Clean Campus
Abilene, Taylor County · Operator: Crusoe, Oracle and OpenAI
200 MW · announced 2025-01
The first Stargate site went live in September 2025 when Crusoe energized two buildings with more than 200 megawatts running Oracle cloud infrastructure for OpenAI workloads. The full plan is an eight building campus of about four million square feet and roughly 1.2 gigawatts, making it the leading example of AI scale power demand landing in a single Texas county.
Issues raised: power, water, transmission, jobs, tax-incentives
Source: Crusoe, 2025-09-30 · On the map
Operating Operating cluster in Westover Hills with more buildings in progress
Microsoft San Antonio Data Center Campus
San Antonio, Bexar County · Operator: Microsoft
Microsoft has built a growing group of data centers in the Westover Hills area of west San Antonio and is adding capacity nearby in Bexar and Medina counties. Local coverage has focused on water demand over the Edwards Aquifer, and Microsoft has funded protection of more than 1,500 acres in the aquifer recharge zone in response.
Issues raised: water, power, tax-incentives, jobs
Source: San Antonio Report · On the map